2002-23 Resolution No. 2002-23
A RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF GRAND TERRACE, STATE OF CALIFORNIA,
ADOPTING THE MEASURE "I" FIVE-YEAR
CAPITAL IMPROVEMENT PROGRAM
WHEREAS, San Bernardino County voters approved passage of Measure I in November,
1989, authorizing San Bernardino Associated Governments, acting as the San Bernardino County
Transportation Authority, to impose a one-half of one percent retail transactions and use tax
applicable in the incorporated and unincorporated territory of the county of San Bernardino, and
WHEREAS; revenue from the tax can only be used for transportation improvement and traffic
management programs authorized in the Expenditure Plans set forth in Ordinance No. 89-1 of the
Authority, and
WHEREAS, Expenditure Plans of the Ordinance require each local jurisdiction . receiving
revenue from the tax to expend those funds pursuant to a Five-Year Capital Improvement
Program and a Twenty-Year Transportation Plan adopted by resolution of the local jurisdiction,
and
WHEARAS, the Twenty-Year Transportation Plan has been previously adopted, and is on file
� with the San Bernardino Association of Governments (SANBAG), and
NOW, THEREFORE, BE IT RESOLVED that:
1) The City Council of the City of Grand Terrace, State of California, hereby adopts the Measure I
Five-Year Capital Improvement Program, a copy of which is attached to this resolution.
2) In case of an emergency, such as flooding or other major necessary road expenses, these
funds could be reallocated.
NOW THEREFORE, BE IT FURTHER RESOLVED that the City Council of the City of Grand
Terrace, State of California, hereby adopts the Measure I Five-Year Capital Improvement
Program.
PASSED, APPROVED AND ADOPTED by the City Council of\the City of Grand Terrace,
California at a regular meeting held on the 22"d day of August 2002:
ATTEST:
City Clerk of the City of Gran6/Terrace Mayor of the City of Grand Terrace
and of the City Council thereof. And of the City Council thereof.
r-- I, BRENDA STANFILL, City Clerk of the City of Grand Terrace, do hereby certify that the
foregoing Resolution was introduced and adopted at a regular meeting of the City Council of the
City of Grand Terrace held on the 22"d day of August, 2002, by the following vote:
AYES: Councilmembers Hlilkey, Larkin, and Ferre; Mayor Pro Tem Garcia and
Mayor Buchanan
NOES: None
ABSENT: None
ABSTAIN: None
Brenda Stanfill
City Clerk
Approved as to form:
City Attorney ` 1
City olr�,__,and Terrace
MEASURE I FIVE YEAR PLAN 2001/2006
(Adopted August 22, 2002)
YEAR STREET & LIMITS IMPROVEMENT COST ESTIMATE
2002-04 I Union Pacific Railroad Bridge at Barton Road I Replacement and widening of Bridge I 1 I $140,000
2000-02 I Michigan St. Barton Rd. to Commerce Wy. I Upgrade to Major Highway&Signal I 1 I $105,000
Relocation
2000-02 Barton Rd. at Vivienda Upgrade Barton Rd. to Major Highway incl. 1 $30,000
sidewalks and ADA Ramp at the corner&
storm drain
2001-02 Mt. Vernon St. Upgrade to Secondary Highway w/raised 1 $196,000
Grand Terrace Rd./Canal St. median &City entry sign
(City Entry) to 300 ft. south
$600,000
2000-01 Minona Dr. Full Street Reconstruction 3 $29,032
Kingston St. to Eton St.
2000-01 I Holly St. I Pavement Rehab-OS I 3 I $31,589
Eton St. to Arliss Dr.
2000-01 I Fairburn Dr. I Full Street Reconstruction I 3 I $55,186
Kingston St. to Miriam Wy.
2001-02 I Arliss Ct. I Full Street Reconstruction I 3 I $13,569
Arliss Dr. to north end
2001-02 I Arliss Dell I Pavement Rehab. -OS I 3 I $8,379
Arliss Dr. to north end
2001-02 I Arliss Dr. I Pavement Rehab.-OS I 3 I $13,733
Arliss Dell to Eton Dr.
2001-02 Arliss Dr. Pavement Rehab. -OS 3 $16,543
Preston St. to Arliss Dell
2001-02 I Arliss Dr. I Pavement Rehab. -OS I 3 I $22,047
Eton Dr. to Arliss Wy.
2003-04 I City-Wide I Slurry Program 12 I $90,000
1
`-::�)4-05 Raven Wy. Pa'v.,_ nt Rehab. -OS 3 $47,178 �
Wilmac Ave. to Oriole St.
2004-05 I Raven Wy. I Pavement Rehab. —OS I 3 I $26,361
Michigan St. to Vivienda Ave.
2004-05 I Vivienda Ave. I Pavement Rehab. -OS I 3 I $26,584
Tanager St. to Pico St.
Total Measure I CIP $1,449,022
Contact: Steve Berry SANBAG's Measure I Revenue Estimate (5 yrs.) $ 849,022
909-430-2226 Fund Balance as of June 30, 2000 681,577
TOTAL AVAILABLE: $1,530,599
NOTES:
1 = Transportation/Traffic Projects
2= Max. expenditures of general program categories shall not exceed 50%of SANBAG's total annual forecast revenue for the jurisdiction.
3= Originally, we proposed Measure I to cover only 50%of the cost of projects related to street reconstruction and pavement, saving 50%for
transportation/Circulation projects. Over the years, for lack of other revenue sources, we have increased to 60% and to 75%since last year. The
other 25% is paid from Redevelopment funds for gas tax funds.
2
8/29/2uu-z Street Rehabiifc,ion Program Projects by Fiscai Year
(1994-2011)
Contribution
PRIORITY ROAD NAME FROM ROAD TO ROAD WDTH LGTH AREA RTG IMP Est Cost Measure I RDA
1999-2000 MINONA DR KINGSTON ST ETON DR 33 1173 38,709.23 20 RS 38,709.23 29,031.92 9,677.31
Total1999-2000 29,031.92 9,677.31
2000-01 HOLLY ST ETON DR ARLISS DR 33 1021 38,694.45 56 OS 42,118.07 31,588.55 10,529.52
2000-01 FAIRBURN DR KINGSTON ST , MIRIAM WY 33 1115 36,790.94 36 RS 73,581.88 55,186.41 18,395.47
Total2000.01 86,774.96 28,924.99
2001-02 ARLISS CT ARLISS DR NORTH END 33 288 9,502.33 56 RS 19,384.76 13,569.33 5,815.43
2001-02 ARLISS DELL ARLISS DR NORTH END 33 178 5,867.30 58 OS 11,969.30 8,378.51 3,590.79
2001-02 ARLISS DR ARLISS DELL ETON DR 33 291 9,616.60 58 OS 19,617.86 13,732.50 5,885.36
2001-02 ARLISS DR PRESTON ST ARLISS DELL 33 351 11,584.81 57 SO 23,633.01 16,543.11 7,089.90
2001-02 ARLISS DR ETON DR ARLISS WY 33 468 15,438.86 55 OS 31,495.26 22,046.69 9,448.58
Total2000-01 74,270.13 39,907.67
2002-03 MICHIGAN ST FLAMINGO ST PICO ST 38 268 10,179.71 59 RS 21,173.80 15,880.35 5,293.45
2002-03 MICHIGAN ST PICO ST VAN BUREN ST 38 1325 50,346.69 58 SO 104,721.12 78,540.84 26,180.28
Total2002-03 94,421.20 31,473.73
2003-04 City Wide Slurry Program Total 2003-04 90,000.00
2004-05 RAVEN WY WILMAC AVE ORIOLE AVE 33 946 31,202.18 46 RS 67,396.72 47,177.70 20,219.01
2004-05 RAVEN WY MICHIGAN ST VIVIENDA AVE 33 528 17,434.22 59 RS 37,657.92 26,360.54 11,297.37
2004-05 VIVIENDA AVE TANAGER ST PICO ST 33 533 17,581.94 53 RS 37,977.00 26,583.90 11,393.10
Total2004-05 100,122.14 42,909.49
2005-06 WESTWOOD LN WESTWOOD ST SOUTH END 24 421 10,093.02 46 RS 22,204.64 47,177.70 5,551.16
2005-06 FLAMINGO ST MICHIGAN ST EAST END .33 266 8,768.39 59 RS 19,290.46 26,360.54 4,822.61
2005-06 KINGSTON ST ARLISS DR ETON DR 33 795 26,240.44 55 OS 57,728.96 26,583.90 14,432.24
Total2005.06 74,418.04 24,806.01
2006-07 GRAND TERRACE RD VIVIENDA AVE NEWPORT AVE 40 1562 62,482.44 58 137,461.37 96,222.96 41,238.41
Total2006.07 96,222.96 41,238.41
2007-08 MICHIGAN ST LAD ERA ST RAVEN WY 44 340 14,960.00 68 OS 22,440.35 16,830.26 5,610.09
2007-08 MICHIGAN ST TANAGER ST FLAMINGO ST 38 265 10,069.00 63 OS 15,103.11 11,327.33 3,775.78
2007-08 MICHIGAN ST RAVEN WY TANAGER ST 41 275 11,275.00 69 OL 16,913.03 12,684.77 4,228.26
Project Cost 40,842.36 13,614.12
1
_ r
8/29/2002 Street Rehabilitation Program Projects by Fiscal Year
(1994-2011)
PRIORITY ROAD NAME FROM ROAD TO ROAD WDTH LGTH AREA RTG IMP Est Cost Measure I RDA
2007-08 PICO ST DICKENS CT SANBURG CT 41 167 6,865.00 68 OS 6,865.07 5,148.80 1,716.27
2007-08 PICO ST DICKENS CT SANBURG CT 41 148 6,068.00 68 OS 6,068.00 4,551.00 1,517.00
2007-08 GARDEN CT PICO ST NORTH END 33 473 15,605.00 68 OS 15,605.44 11,704.08 3,901.36
2007-08 PICO ST KINGFISHER RD TRANSITION 41 581 23,802.00 68 OS 23,801.52 17,851.14 5,950.38
52,340.04 39,255.03 13,085.01
Total2007-08 106,796.52 80,097.39 26,699.01
2008-09 MINONA CT MINONA DR SOUTH END 33 349.56 11,535.00 63 OS 11,535.33 8,651.50 2,883.83
2008-09 MINONA DR ETON DR PRESTON ST 33 498.48 16,450.00 68 OL 16,449.96 12,337.47 4,112.49
2008-09 ETON DR MINONA DR MIRIAM WY 33 325.91 10,755.00 65 OS 10,755.03 8,066.27 2,688.76
2008-09 VICTORIA ST PRESTON ST BARTON RD 22 660.19 14,524.00 68 SO 14,524.14 10,893.10 3,631.03
Total2008-09 53,264.46 39,948.35 13,316.12
2009-10 CANAL ST VICTORIA ST CARHART AVE 33 1,431 47,217.00 68 OS 59,021.57 44,266.18 14,755.39
2009-10 NEWPORT AVE CANAL ST CITY LIMITS 28 1,559 43,665.00 64 OS 43,664.63 32,748.47 10,916.16
2009-10 VIVIENDA AVE BARTON RD VIVIENDA CT 33 488 16,114.00 68 SO 16,114.09 12,085.57 4,028.52
Total2009-10 118,800.29 89,100.22 29,700.07
2010-11 DOS RIOS AVE PALM AVE COUNTRY CLUB 33 577 19,035.00 65 OS 19,035.01 14,276.26 4,758.75
2010-11 WARBLER AVE DE BERRY ST DE SOTO ST 33 265 8,745.00 69 SO 8,745.12 6,558.84 2,186.28
2010-11 WESTWOOD ST HONEY HILL DR EAST END 24 1,149 27,578.00 66 SO 27,577.68 20,683.26 6,894.42
2010-11 FREEMONTIA AVE LADERA ST NAPA CT 33 375 12,361.00 63 OS 12,360.97 9,270.72 3,090.24
2010-11 ORIOLE AVE KENTFIELD ST VAN BUREN ST 33 274 9,037.00 64 OS 9,036.70 6,777.52 2,259.47
Total2010-11 76,755.47 57,566.60 19,188.87
TBA BARTON RD 1-215 BRIDGE 64 886 56,674.78 36 SO 85,012.18 59,508.52 25,503.65
TBA MT.VERNON AVE BARTON RD MINONA ST 52 586 30,470.47 58 SO 45,705.70 31,993.99 13,711.71
TBA MT.VERNON AVE DE BERRY ST DE SOTO ST 62. 297 18,388.01 49 SO 27,582.01 19,307.41 8,274.60
TBA MT.VERNON AVE CENTER CITY CT BARTON RD 62 500 30,970.54 49 SO 46,455.82 32,519.07 13,936.74
TBA MT.VERNON AVE VAN BUREN ST DE BERRY ST 62 1,325 82,143.24 58 SO 123,214.86 86,250.40 36,964.46
MT.VERNON AVE DE SOTO ST CENTER CITY CT 62 522 32,348.74 51 OS 48,523.11 33,966.18 14,556.93
Total 291,481.50 263,545.58 72870.38
BARTON RD PRESTON ST GRAND TERRACE RD 62 775 48,052.00 64 OS 72,078.43 54,058.82 18,019.61
BARTON RD ARLISS DR PRESTON ST 62 2,245 139,166.00 68 OS 208,749.66 156,562.25 52,187.42
Project Cost 280,828.09 210,621.07 70,207.02
2