Loading...
01/23/1984'1 CITY OF GRAND TERRACE COUNCIL MINUTES SPECIAL MEETING - JANUARY 23, 1984 A special meeting of the City Council of the City of Grand Terrace was called to order in the City Hall Building No. 4, 22795 Barton Road, Grand Terrace, California, on January 23, 1984, at 5:35 p.m. PRESENT: Hugh J. Grant, Mayor Jim Rigley, Mayor Pro Tempore Tony Petta, Councilman Roy W. Nix, Councilman Barbara Pfennighausen, Councilwoman Seth Armstead, City Manager Ivan Hopkins, City Attorney Joe Kicak, City Engineer Myrna Erway, City Clerk ABSENT: None CIVIC CENTER CONSTRUCTION - EARTHWORK City Manager Armstead advised that at the construction meeting of January 18, Architect Larry Wolff presented a letter from Maveric Construction requesting additional funds for the earthwork; requested this meeting due to the amount requested. Architect Larry Wolff advised that grading of the site began shortly before the holidays; there was a rain delay between Christmas and New Years, then the grading proceeded; he was advised January 5 that the contractor and subcontractor were having difficulty obtaining compaction; discussed alternatives to alleviate the problem with the soils engineer, who had a representative on site at all times. As the problems became more evident, determined the job should betemporarily stopped and the soils engineer should conduct additional testing to the original tests conducted 14-15 months previously, in an effort to clarify the problem. John Byerly, the soils engineer, stated initial soils tests were conducted October 22, 1982 on the Civic Center site, at which time test borings were placed at different depths; four borings were extended from 14-18 feet below the ground surface and samples were analyzed for various properties, including moisture; the results indicated relatively dry, innocuous moisture contents that were substantially below optimum moisture content; no hint of moisture problems were seen. Provided recommendations for preparing the site to assure uniform foundation support. Prior to grading operations which began December 20, 1983, nearly twice the normally expected amount of rainfall occurred in the fall and early winter; the moisture content was not uniform; some areas were saturated and other areas near M1/ 3/84 the surface were fairly dry; the contractor was having substantial difficulty obtaining compaction; a discussion was held December 23 relative to the inability to obtain compaction using static sheepsfoot roller equipment, which could be an indication the moisture content was too dry; therefore, suggested using alternative equipment, a vibratory sheepsfoot roller, to obtain proper compaction. Over Christmas there was very heavy rainfall which inundated the site; the contractor backfilled the area, but water got into the backfill and created saturated conditions as much as 4-5% over the optimum. For two weeks the contractor aerated, bladed and worked the soil, achieving marginal compaction tests; at that time supplementary investigation tests were conducted which revealed the present soil condition which consists of a very wet layer of soil at depths 3-6 feet which is quite soft and totally incompatible with vibratory compactor equipment. The wet soil layer acts like a sponge for that equipment, minimizing the effectiveness of the compactor to achieve proper compaction; recommended in a supplementary report that use of the vibratory compactor be discontinued and that static sheepsfoot roller equipment be used immediately. Consideration was given to mixing dry sand with the wet soil to reduce the moisture content, thereby increasing the ability to get compaction rather than waiting for the soil to dry; believes the compaction at the footing is still poor, but believes it is adequate for assuring foundation support for the structure; feels the way it is now, no further work is needed; feels mixing the sand will allow the contractor to proceed immediately. Architect Larry Wolff advised the Byerly firm was originally selected a year and a half ago to provide a preliminary soils analysis for the fire station and the civic center; his recommendations from the initial report were provided to him and the City Engineer, and were incorporated into the earthwork section of the specifications, with the stipulation that the contractor would be required to provide all testing and pay all costs for testing by a qualified soils engineer; Mr. Byerly has been retained by the contractor, but is also working for the City and Mr. Wolff. Councilman Petta questioned if the soil condition on this site would be the same in other areas of the City, and whether there was a way to pre -determine this condition could exist. Mr. Byerly stated soil conditions vary from site to site; indicated that based on his report, there was no way to pre -determine the present condition; there are methods available to evaluate the potential of rainfall infiltration, but those kinds of tests are not normally done for foundation studies; indicated the only way to determine the existing condition is from the type of testing which was conducted two weeks ago. Mayor Grant questioned if it wouldn't be logical to assume that any appreciable rainfall would indicate that precautions should be taken in terms of further testing as the process developed and the weeks went by, considering the size of the structure to be built; questioned if there is no evidence anywhere in the City of appreciable difference in the percentage of compaction based on the rainfall. Mr. Byerly stated the rainfall after the grading began influenced the moisture content present at this time; indicated has performed services for marry other sites which have not been affected by the same rainfall; in 20 years of experience has not encountered this type of condition. Page 2 - 1/23/84 I Mr. Wolff stated the up to the architect; were well within the decision of whether additional soils testing is required is felt the preliminary foundation investigation tests conducted accepted practices. City Attorney Hopkins requested clarification of Mr. Byerly's statements relative to the compaction being adequate as it is now. Mr. Byerly stated one-third of the work has passed the compaction test, with two-thirds yet to be accomplished. Mr. Hopkins questioned if Mr. Byerly recommends mixing sand with the soil. Mr. Byerly indicated that would be his recommendation, as well as other recommendations, each of which will cost money; it will take a long time to get the moisture out of the soil without mixing a dry import. Attorney Hopkins questioned and Mr. Byerly responded that he did not feel that his original report was misleading in any way to the contractor. Mr. Hopkins questioned if Mr. Byerly felt the City should be responsible for the additional cost; Mr. Byerly felt that is not his responsibility; felt his report reflected the conditions which existed at that time, and that the present conditions were not reasonably forseeable. Councilwoman Pfennighausen referenced the last paragraph of a letter from Larry Wolff indicating there appears to be a hard, dense layer below the moist layer, keeping the moisture in the soil; questioned if the initial tests indicated this, whether the heavy rainfall after testing would indicate the need for further testing prior to grading, and whether the dense layer is not allowing the water to percolate away from the area, which could cause continuing problems. Mr. Byerly stated this condition is unique and was not anticipated; gave assurance that any water accumulation after the structure is completed would not adversely affect the foundation. Councilman Rigley questioned the number of penetrations made and the amount of area covered in the initial testing. Mr. Byerly stated four borings eight inches in diameter were done, and the soil evaluated at those locations, which reflected uniform conditions. Attorney Hopkins questioned if the architect set forth the method of compaction in the specifications - whether they specify how to achieve compaction or that it is to be achieved. The architect stated the recommendations obtained from the initial investigation to prepare the site were inserted in the earthwork specifications which indicated the method of obtaining compaction; feels the existing problem could not have been foreseen without additional testing which is not normally done; had the additional testing been required and the resulting recommendations included in the bid documents, the City would have paid a corresponding amount to get the work completed. Councilman Nix questioned how this project is unique from construction elsewhere in the City. Mr. Byerly stated it is not uncommon to have a condition develop on a site that is different than anticipated; to eliminate all possible risk would require considerable expenditures; feels in most cases the tests conducted would have defined all the problems and construction would have gone smoothly, as with the fire station. Larry Wolff stated he feels the contractor and subcontractor have complied with the specifications, doesn't feel the problems encountered could have been Page 3 - 1/g3/84 discovered under normal or accepted practices of soils engineering, and doesn't feel he has mislead the contractor. Doesn't wish to see the City expend the additional funds, but also doesn't see how the contractor or subcontractor can be expected to bear the additional costs, since all work has been performed as requested, with no results. Attorney Hopkins questioned if the method set forth in the specifications to achieve compaction has been used throughout, or whether the method has been changed on the soils engineer's advice. Mr. Wolff stated the specifications did not specify the equipment to be used or procedures for its use. Councilman Nix felt the specifications state a condition, the end result to be achieved, and some indication of what is to be done to comply with the specifications, but do not include specific details of how to do the job, or the type of equipment to be used. Attorney Hopkins questioned and Mr. Byerly confirmed he was hired by the City to perform the soils investigation which was used in the bid documents, and has now been retained by the general contractor for the construction phase of the project. Attorney Hopkins questioned if Mr. Byerly's advice to switch equipment was in the capacity of employment with the general contractor; Mr. Byerly responded affirmatively, as a consultant. Roy Taylor, Maveric Construction, the general contractor, stated he feels the testing and report were within reason and does not feel the City would have paid for the type of testing needed to indicate the present situation prior to being aware there could be a problem. Stated there is a publication called the "Green Book" which has been adopted by San Bernardino and Riverside Counties, by the City of San Bernardino, and is used by most large counties or cities. This book makes provisions for unforeseen work and the municipalities in which it occurs are liable for that cost; indicated the City has done everything that should be done, but in this case it didn't work out; doesn't see where anyone is to blame. Councilman Nix stated the City must question if this condition could not have been foreseen; advice was given to plan for a 2% contingency; this will expend the contingency for the entire project, which indicates there is a problem either with the planning or the input received. City Manager Armstead questioned whether the estimated cost of $27,302 will ensure the proper compaction for the footings. Mr. Wolff stated the estimated costs listed in his letter of January 23, 1984 do not reflect the amount being requested; the contractor submitted a formal price quotation of $21,402.57, plus an additional amount of $9,465.36 to import and mix the soil in a letter dated January 19; feels both should be done to achieve a reasonable level of success to finish the grading; indicated no guarantee is attached to the price quotation received. John Byerly felt the importation of dry sandy soil would facilitate the job greatly, and that the price proposed for the importation is prudent. The architect questioned and the subcontractor responded he felt this should take care of the problem, but would give no guarantee. The contractor stated if this isn't done now, and there is more rainfall, it will create serious problems and cost excessively more than the present quotation; stated the soil in its present condition is not compactible; if soil is not imported and the job is delayed 2-3 months, the City would receive an exorbitant bill. The grading should have been Page 4 - 1/23/84 completed in 10 days, with footings being poured now; if the soil is imported, compaction should take another 7-10 days. The City Engineer questioned the borrow site and the suitability of the import; the borrow site is the river on Waterman; Mr. Byerly felt the import would be suitable. Recess was called at 7:31 and reconvened at 7:45 p.m., with all members present. Councilman Rigley recommended the City pay 50% of the involved expenses. The contractor disagreed, feeling it is not his responsibility and that each day on this project not producing costs him $500 per day in office and business overhead, which hasn't been charged to the City. Councilman Nix disagreed with negotiating the costs; is not convinced the City is liable; feels a licensed bidder who knows the business, the area and construction should be bidding to do a job; had an act of God occurred, could agree with the unforseeable circumstances; has heard nothing to convince him this situation should not have been forseeable by people in this business and an issue which the contractor accepts and knows is part of his responsibility when he bids a job. Requested a review and interpretation of the contract by the City Attorney relative to the contractor's responsibilities. Attorney Hopkins disagreed that you cannot contract for and receive guaranteed results; compaction is one of the more common items for which you contract and get results; manly contracts are guaranteed; otherwise there would be no reason to bid on time and materials. The contractor based his judgment, in bidding the project, on the data supplied by the soils engineer; if that was inaccurate, due to a change of conditions, not due to his inaccuracy, but to changing conditions, the City should have been made aware of that, and possibly should not have to pay the price for the changing conditions; that is the judgment someone has to make; is not convinced the City is legally required to pay any additional amount, and isn't convinced the contractor isn't legally obligated to perform. Questioned the architect relative to setting forth a method, because if the City set forth a method and did not ask for results, it would be asking him to do a job as the City wanted the job done, and in that case would be responsible for the total cost. Advised the contract documents set forth a method for resolving disputes; recommended arbitrating and letting a third party decide the issue if it cannot be resolved at this time. The contractor felt he should seek legal advice; stated the specifications indicate that if the owner and contractor reach an impasse, the architect will make a decision; stated if the City does not make a decision at this meeting, and any rainfall or element occurs to jeopardize the work accomplished to date, believes the City will be liable. Councilman Petta questioned the price quotation, feeling it is exorbitant; the contractor provided a listing of equipment rental rates and stated the price quotations are 40% less than those recommended by the contractors' association; has requested the same rates listed in the bid; would have increased the prices 15-20% if this were a bid situation; guaranteed 1500 yards of soil will be brought in, but will not guarantee more will not be required for compaction of the Page 5 - 1/g3/84 remainder of the site. Councilman Petta questioned why 90% compaction is required for the pavement areas. The soils engineer advised a firm sub -grade must be provided so the pavement won't yield from fatigue and will have a normal life of 20 years. The City Engineer stated the City and the State require 95% compaction in the last 6 inches and 90% in the last two feet. Councilman Nix felt the situation of the soils engineer being retained by both the City and the contractor should not have been allowed; expert advice is needed regarding this situation; this individual is not in a very good position to state the City didn't do its job or that something was improperly or inadequately done. Mr. Byerly stated the key issue is who is liable for the condition which exists, not who is responsible, feeling no one is at fault for the existing condition. Attorney Hopkins concurred the issue is who has legal responsibility to correct the condition; the question is was the job bid for a finished product, or was the bid based on some conditions which have changed, and because of those changed conditions, is that the responsibility of the City. Suggested considering the option of the architect making a decision, with either party having the right to appeal the decision to arbitration, as specified in the contract. Architect Larry Wolff recommended proceeding with the general contractor's request for additional compensation, based upon the soil engineer's proposed recommendation in finalizing the earthwork and compaction; feels the work which has been performed should be compensated; based upon quotations and estimates given, compared to some of the trade references, feels there are no great disparities in cost, and sees no reason not to proceed; feels what is best for the entire project is what is best for the community; therefore, recommended proceeding with the proposed change order. City Attorney Hopkins stated Council has 30 days to appeal the architect's decision to an arbitrator, as specified in the contract; recommended that Council not waive its legal rights if the architect's decision is accepted. Motion by Councilman Rigley, Second by Councilman Petta, to accept the Architect's decision, reserving the right to determine at any time in the future the responsibility, if any further work is required. Attorney Hopkins advised if this Motion carries, Council will have waived the right of appeal; stated the Motion is to accept the architect's decision to approve the change order, with the caveat that the City is not accepting responsibility for any future occurrences. Councilman Nix stated the architect has made a decision and the job will proceed; Council has 30 days to decide whether or not to appeal; if the City appeals and loses, it pays - if it appeals and wins, it doesn't pay; however, the Motion, as made, closes the door on that option. Following clarification, the Motion failed 2-3, with Councilmen Rigley and Petta voting AYE. Attorney Hopkins clarified Council rejected the Motion to waive the 30-day right to appeal; did not indicate whether or not it would appeal; the City cannot cancel n the architect's decision to honor the change order and for the City to pay, but it I I has 30 days to appeal that decision. I I 1/9Pae6 3/84 L' The contractor felt he needs to consult his attorney; will resume work on the project as soon as possible, feeling otherwise if he leaves the grounds unattended, the arbitrator could determine that the architect told him to proceed, at which time it becomes his responsibility. ADJOURN - The Special Meeting adjourned at 8:46 p.m. The next regular meeting wi7T-Fe held January 26, 1984 at 5:30 p.m. Page 7 - 1/23/84 Respectfully submitted, ityCe c APPROVED: May r