G.7 - Status Update on Priority Capital ProjectsStatus Update
Priority Capital Projects
April 27, 2021
Fitness Park Shade Structure
2021 Road Repair & Rehabilitation
Richard Rollins Community Park Wheelchair Swing
West Barton Bridge Replacement
Wireless Internet at Pico Park and Rollins Park
HSIP Cycle 9 –Guardrail Improvements
Mt. Vernon Slope Stabilization
Fitness Park Shade Structure
Project Description Status
Installation of six structural supports and three
shade sails at Fitness Park.
Project Cost: $68,700
Funding Sources: General Fund
Waiting for Poles –
Expected Delivery Date is May 5, 2021
Milestones:
1.May 5, 2021 -Delivery of Poles to City
2.May 19, 2021 -Completion of Pole Installation
3.May 20, 2021 -Provide Shade Sail Manufacturer Aerial Dimensions
4.July 8, 2021 -Delivery of Shade Sails
5.July 15, 2021 -Completion of Shade Sail Installation
Fitness Park Shade Structure
Fitness Park Shade Structure
Wheelchair Swing at Richard Rollins
Community Park
Project Description Status
Installation of a wheelchair swing at Richard
Rollins Community Park
Project Cost: $10,000
Funding Sources: California State Park Grant
Waiting for Swing –
Expected Delivery Date is May 21, 2021
Milestones:
1.May 21, 2021 -Delivery of Wheelchair Swing
2.June 4, 2021 -Completion of Swing Installation
Wheelchair Swing at Rollins Park
Wheelchair Swing at Rollins Park
Wireless Internet at Pico Park and Rollins Park
Project Description Status
Installation of wireless internet for Public Use at
Pico Park and Richard Rollins Community Park.
Project Cost: $35,775
Funding Sources: Cares Act
Waiting for Cable Service Installation
Milestones:
1.April 29, 2021 -Installation of Internet Service at Richard Rollins Community Park
2.May 6, 2021 -Installation and Configuration of Wireless Router at Richard Rollins Community Park
3.May 19, 2021 -Installation of Internet Service at Pico Park
4.July 8, 2021 -Installation and Configuration of Wireless Router at Pico Park
2020/2021 Road Rehabilitation
Project Description Status
Resurface 10 City streets with cape seal treatment and
resurface Barton Road with mill and overlay treatment east
of Honey Hill.
The 10 streets that will receive a cape seal treatment
include: Terrace Ave, Walnut Ave, Grand Terrace Ct, Carhart
Ave, Minona Dr, De Soto Ave, Oriole Ave, Garden Ave, Pico
Ave, and Fremontia Ave.
Project Cost: $550,000
Funding Sources: Measure I, Gas Tax RMRA, General Fund
MOE)
Construction Started on 4/22/2021
Milestones:
1.April 22, 2021 –Start Construction
2.July 12, 2021 -Complete Construction
FY 2020-21 Road Rehabilitation
CAPE SEAL STREETS:
1.Terrace Ave
2.Walnut Ave
3.Grand Terrace Ct
4.Carhart Ave
5.Minona Dr
6.De Soto Ave
7.Oriole Ave
8.Garden Ave
9.Pico Ave
10.Fremontia Ave
MILL & OVERLAY STREET:
1. Barton Rd E/of Honey Hill
FY 2020-21 Road Rehabilitation
Street From To Length Width Area
FREMONTIA AVE REED AVE W MAIN ST 1,254 32 40,128
TERRACE AVE VIVIENDA AVE WALNUT AVE 828 21 17,388
DE SOTO ST WARBLER AVE ORIOLE AVE 927 32 29,664
GRAND TERRACE CT GRAND TERRACE RD CDS 278.37 32 8,907
CARHART AVE VIVIENDA CT CANAL ST 851 32 27,232
ORIOLE AVE LA PAIX ST DE BERRY ST 527 32 16,864
GARDEN AVE CDS PICO ST 240 32 7,680
MINONA DR ETON DR PRESTON ST 482 32 15,424
WALNUT AVE TERRACE AVE BURNS AVE 948 32 30,336
PICO ST MOUNT VERNON AVE ORIOLE AVE 1,263 40 50,520
RENE LANE MICHIGAN AVENUE WEST END 17,300
BARTON ROAD HONEY HILL WESTERN DRIVEWAY 1,060.00 48 50,880
BARTON ROAD WESTERN DRIVEWAY EAST CITY LIMIT 900 24 21,600
West Barton Road Bridge Replacement
Project Description Status
Removal of the West Barton Bridge over the
abandoned Union Pacific rail line and replacement
with engineered fill supporting a standard two-lane
roadway. City of Colton is the Lead Agency.
Project Cost: $3,562,480
Funding Sources: Federal Bridge Program, Gas Tax
Preliminary Engineering and Environmental Document
-Completion Expected July 2021.
Milestones:
1.July 2021 -Preliminary Engineering/Environmental Document Completion
2.May 2022 -Final Engineering Completion
3.December 2022 -Right-of-Way Acquisition Completion
4.March 2023 -Start Construction
5.February 2024 –Project Completion
West Barton Bridge Replacement
HSIP Cycle 9 –Guardrail Improvements
Project Description Status
Installation of guardrail improvements on Mt.
Vernon Ave, Barton Rd, Vivienda Ave and Vista
Grande
Project Cost: $648,000
Funding Sources: Federal HSIP
Preparing Environmental Certification –
Preliminary Engineering/Environmental Study (PES)
Natural Environment Study (Minimal Impact)
Completion Expected by May 2021
Milestones:
1.May 2021 –Completion of PES
2.July 2021 –Award of Contract for Final Engineering (PS&E)
3.August 2021 –Funding Obligated by Caltrans/Authorization to Proceed to Construction (E-76)
4.September 2021 –Advertise for Construction Bids
5.November 2021 -Award Construction Contract
6.January 2022 -Project Completion
HSIP Cycle 9 –Guardrail Improvements
BARTON ROAD
HSIP Cycle 9 –Guardrail Improvements
VISTA GRANDE WAY
HSIP Cycle 9 –Guardrail Improvements
MT VERNON AVENUE
HSIP Cycle 9 –Guardrail Improvements
VIVIENDA DRIVE
Mt Vernon Slope Stabilization
Project Description Status
Grant Application to stabilize the slope along the
east side of Mt. Vernon Avenue north of Grand
Terrace Road.
Project Cost: $3,200,000
Funding Sources: Federal HSIP
Waiting for FEMA to notify grant recipients
Milestones:
1.July 2021 to September 2022 –FEMA Notification of Award (4 to 18 months depending on FEMA review processes)
Mt. Vernon Slope Stabilization